Delivery tracker: official commitments

74 formal commitments by public bodies, each linked to its original decision. A stage is shown as reached only where dated evidence exists. These are official commitments; Facts Count’s own proposals are in the action plan.

74 commitments
The cost of living · 10 commitments · 9 with dated evidence · 0 past due date

Committed by UK Government In progress

No date set

Right to Buy (council tenants)

Let eligible council tenants buy their Portsmouth Homes property at a discount, after at least three years as a public sector tenant (or in armed forces accommodation); some homes, such as specialist housing for older or disabled people, are excluded.

ApprovedFundedUnder wayCompleted

Status evidence, 10 November 2026: Buying a Portsmouth Homes property (Right to Buy) ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Portsmouth City Council (discount on the sale price) Amount not stated · Discount depends on tenancy length, property type and value, and may be reduced under cost-floor rules

Made 10 November 2026 · Buying a Portsmouth Homes property (Right to Buy) ↗

Not yet published:

  • How many Right to Buy sales Portsmouth completes each year (published nationally by the government; not yet added here).
  • Each sale reduces the council’s stock of homes for rent; replacement is not reported alongside sales.

Issue: The cost of living, Homes and homelessness

Committed by Portsmouth City Council In progress

No date set

Warm Homes: Local Grant

Lead the Warm Homes: Local Grant for Portsmouth and 31 other councils, paying for home energy improvements, delivered locally by Switched On Portsmouth.

ApprovedFundedUnder wayCompleted

Status evidence, 10 November 2026: Warm Homes Local Grant ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Department for Energy Security and Net Zero £34,807,254 · Whole 32-council consortium, not Portsmouth alone

Made 2 July 2026 · £34,807,254 (Award to the whole consortium (government list updated 2 July 2026); no Portsmouth-only figure is published) · Warm Homes: Local Grant – successful local authorities ↗

1 dated record
  1. 10 November 2026 milestone Switched On Portsmouth: the scheme is oversubscribed and no longer taking applications; a waiting list is open while a further government funding decision is awaited. source ↗

Issue: The cost of living, Poverty, jobs and pay

Committed by Portsmouth City Council In progress

Due 31 March 2029

Crisis and Resilience Fund

Run the Crisis and Resilience Fund from 1 April 2026 to 31 March 2029: crisis payments, housing payments, grants to local resilience services and community coordination.

ApprovedFundedUnder wayCompleted

Status evidence, 13 October 2026: Crisis and Resilience Fund ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Ministry of Housing, Communities and Local Government £3,691,344 · Revenue grant, 2026/27 (year one of three)

Made 1 April 2026 · due 31 March 2029 · Crisis and Resilience Fund ↗

6 dated records
  1. 1 April 2026 milestone Crisis and Resilience Fund began, running to 31 March 2029. source ↗
  2. 8 May 2026 milestone Government grant determination allocated £3,691,344 to Portsmouth for 2026/27, paid in monthly instalments. source ↗
  3. 31 August 2026 output 1,012 crisis payment applications received and 428 awards made, totalling £139,707; 323 applications were declined as ineligible. source ↗
  4. 23 September 2026 output 33 resilience grants awarded, worth £748,392, from 47 applications; 90% of the money falls in the fund’s first year. source ↗
  5. 13 October 2026 milestone Council states it has allocated over £1.5 million to local resilience services and over £400,000 to community coordination; funded services not yet listed. source ↗
  6. 13 October 2026 milestone The council reports allocating over £1.5 million to resilience services (food, advice, energy, wellbeing, housing and homelessness help) and over £400,000 to community coordination, which funds the Cost of Living Hub and helpline. These are parts of the fund, not additions to it; the funded services had not yet been listed. source ↗

Issue: The cost of living, Poverty, jobs and pay

Committed by Health and Wellbeing Board In progress

Due 2028

Tackling Poverty Action Plan 2026-2028

Deliver twelve tasks under four priorities: maximising household income, strengthening the local safety net, increasing opportunities and improving wellbeing, and using data to support partnership working.

ApprovedFundedUnder wayCompleted

Status evidence, 23 September 2026: Health and Wellbeing Board, 23 September 2026, item 9: Tackling poverty in Portsmouth ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made 4 March 2026 · due 2028 · Health and Wellbeing Board, 4 March 2026: Tackling Poverty Action Plan 2026-28 (report and Appendix 1) ↗

2 dated records
  1. 4 March 2026 milestone Tackling Poverty Action Plan 2026-2028 presented to the Health and Wellbeing Board, for information. source ↗
  2. 23 September 2026 milestone Delivery update against the twelve tasks presented to the Health and Wellbeing Board. Reported figures cover outputs, not changes in hardship. source ↗

Issue: The cost of living, Poverty, jobs and pay

Committed by UK Government In progress

No date set

First Homes scheme

Let first-time buyers in England buy eligible homes for 30% to 50% below market value, with household income up to £80,000 and a price cap of £250,000 after the discount outside London; councils may set local criteria for the first three months of sale.

ApprovedFundedUnder wayCompleted

Status evidence, 17 October 2024: First Homes scheme: first-time buyer’s guide ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Developers (discount on the sale price) Amount not stated · The discount is given by the developer on new homes, usually through planning agreements; not a government grant

Made 28 February 2022 · First Homes scheme: first-time buyer’s guide ↗

Not yet published:

  • No Portsmouth First Homes local criteria, price cap or number of homes sold was found on the council’s pages (searched 10 November 2026).
  • Whether a new site includes First Homes depends on its planning agreement. Councils’ published notes say national policy stopped requiring a First Homes share of affordable homes in December 2024; this was not confirmed from the current planning framework text. A developer listing the scheme elsewhere does not mean its Portsmouth sites offer it.

Issue: The cost of living, Homes and homelessness

Committed by UK Government Funded

Due 31 March 2027

Homelessness, Rough Sleeping and Domestic Abuse Grant 2026/27

Pay Portsmouth a homelessness, rough sleeping and domestic abuse grant for 2026/27, on condition that the council publishes a homelessness action plan and reports on its use.

ApprovedFundedUnder wayCompleted

Status evidence, 8 May 2026: Homelessness, Rough Sleeping and Domestic Abuse Grant Determination 2026/27 [No 31/8380] ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Ministry of Housing, Communities and Local Government £4,101,246 · Revenue grant, 2026/27

Made 8 May 2026 · due 31 March 2027 · £4,101,246 (Grant determination 31/8380, 1 April 2026 to 31 March 2027. Not to be added to the Rough Sleeping Programme funding) · Homelessness, Rough Sleeping and Domestic Abuse Grant Determination 2026/27 [No 31/8380] ↗

Issue: The cost of living, Homes and homelessness

Committed by UK Government Approved

Due February 2027

Your First Home (equity loan, from 2027)

Help first-time buyers buy an eligible new-build home in England with a deposit of at least 2.5%, a repayment mortgage and a government equity loan of 20% of the price, interest free for five years.

ApprovedFundedUnder wayCompleted

Status evidence, 3 November 2026: Your First Home ↗

Who pays, key dates and what is missing
Funded by
  • Funded by UK Government Amount not stated · Equity loans of 20% of each purchase price; total budget not stated on the guidance page

Made 28 October 2026 · due February 2027 · Your First Home ↗

Not yet published:

  • Applications are expected from February 2027; eligible homes, participating developers and lenders are not yet published.
  • Whether homes in Portsmouth will qualify depends on developers taking part and on local price caps.

Issue: The cost of living, Homes and homelessness

Committed by Portsmouth City Council Approved

No date set

Private rented housing enforcement

Apply an updated Private Sector Housing Enforcement Policy and Civil Financial Penalty Policy, reflecting the Renters’ Rights Act 2025, to breaches and offences from 1 November 2026.

ApprovedFundedUnder wayCompleted

Status evidence, 20 October 2026: Cabinet Member for Community Safety, Leisure and Sport, 20 October 2026: recorded decision ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made 20 October 2026 · Cabinet Member for Community Safety, Leisure and Sport, 20 October 2026: Private Sector Housing Enforcement Policy and Civil Penalty Policy amendments ↗

Issue: The cost of living, Homes and homelessness, Shared housing (HMOs)

Committed by Portsmouth City Council Approved

Due 2029

Homelessness Strategy 2024-2029

Adopt and deliver a five-aim homelessness strategy: prevent homelessness, end rough sleeping, provide the right housing, provide the right support and strengthen joint working, measured by a published suite of measures.

ApprovedFundedUnder wayCompleted

Status evidence, February 2024: Homelessness Strategy 2024-2029 ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made February 2024 · due 2029 · Homelessness Strategy 2024-2029 ↗

1 dated record
  1. February 2024 milestone Homelessness Strategy 2024-2029 published. source ↗

Issue: The cost of living, Homes and homelessness

Committed by Portsmouth City Council Not verified

Due 2026

Corporate Plan 2024-2026

Provide support for people struggling with the cost of living.

ApprovedFundedUnder wayCompleted

No dated evidence of progress has been found; stages are shown hatched.

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made October 2024 · due 2026 · Corporate Plan 2024-2026 (Council Plan 2024) ↗

Issue: The cost of living

Crime and anti-social behaviour · 8 commitments · 5 with dated evidence · 1 past due date

Committed by Health and Wellbeing Board (Safer Portsmouth Partnership) In progress

Due 2028

Community Safety Plan 2025-2028

Reduce crime, anti-social behaviour and harm over three years through four priorities: tackling violent crime (including violence against women and girls and knife crime), reducing drug harm, supporting young people at risk and helping people with complex needs.

ApprovedFundedUnder wayCompleted

Status evidence, 23 September 2026: Health and Wellbeing Board, 23 September 2026, item 10: Community Safety Update ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made 25 June 2025 · due 2028 · Our priorities and plan: Community Safety Plan 2025-2028 ↗

2 dated records
  1. 25 June 2025 milestone Health and Wellbeing Board approved the Community Safety Plan 2025-2028. The plan sets no fixed numerical targets and has no plan-level budget. source ↗
  2. 23 September 2026 milestone Progress update on the Community Safety Action Plan 2025-28 presented to the Health and Wellbeing Board, for information. source ↗

Issue: Crime and anti-social behaviour

Committed by Police and Crime Commissioner Funded

No date set

Summer anti-social behaviour funding 2024

Fund extra community wardens, youth outreach and patrols in anti-social behaviour hotspots in Portsmouth (£150,000 of a £750,000 force-wide release).

ApprovedFundedUnder wayCompleted

Status evidence, 28 August 2024: Police Commissioner releases £750k for community wardens (28 August 2024) ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Police and Crime Commissioner (Home Office hotspot grant) £150,000 · Portsmouth share of a £750,000 release, 2024

Made August 2024 · £150,000 (Portsmouth allocation in the Commissioner's release of 28 August 2024) · Police Commissioner releases £750k for community wardens to prevent a spike in anti-social behaviour over the summer period ↗

Issue: Crime and anti-social behaviour

Committed by Portsmouth City Council Approved

Originally proposed by Labour group amendment Proposal and vote →

No date set

Capital programme 2026/27: schemes added by amendment

Deliver four schemes added to the 2026/27 capital programme: a raised zebra crossing on Lawrence Road, traffic calming on Highbury Grove, five deployable CCTV cameras for Charles Dickens ward and more accessible play equipment.

ApprovedFundedUnder wayCompleted

Status evidence, 24 February 2026: Full Council, 24 February 2026, minute 10: Budget and Council Tax 2026/27 (recorded votes) ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Portsmouth City Council (capital programme) moved within budget: £211,000 · Capital, 2026/27, moved from other schemes
  • Funded by Neighbourhood Community Infrastructure Levy Match funding · The rest of the £120,000 Lawrence Road crossing

Made 24 February 2026 · £211,000 (Reallocated within the capital programme; the Lawrence Road crossing also draws on neighbourhood Community Infrastructure Levy) · Full Council, 24 February 2026: minutes with Appendices 1 to 3 (budget amendments), confirmed on 17 March 2026 ↗

Issue: Crime and anti-social behaviour, Air pollution and traffic, Council services and finances

Committed by Hampshire and Isle of Wight Fire and Rescue Authority Approved

Due 31 March 2030

Safety Plan 2025-2030

Deliver the Safety Plan (community risk management plan) from 1 April 2025 to 31 March 2030. It names no Portsmouth-specific service changes; it identifies very high dwelling-fire risk areas, mainly in the cities.

ApprovedFundedUnder wayCompleted

Status evidence, 12 February 2025: Fire Authority approve HIWFRS Safety Plan for 2025-2030 ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made February 2025 · due 31 March 2030 · Safety Plan ↗

Issue: Crime and anti-social behaviour

Committed by Police and Crime Commissioner Approved

Due 2028

Police and Crime Plan 2024-28

Commission partner agency interventions to tackle anti-social behaviour, and hold the Chief Constable to account for tackling it.

ApprovedFundedUnder wayCompleted

Status evidence, 1 November 2024: PCC Donna Jones launches her new Police and Crime Plan 2024-2028 ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made 1 November 2024 · due 2028 · Police and Crime Plan 2024-28: More Police, Safer Streets ↗

1 dated record
  1. 1 November 2024 milestone Police and Crime Plan 2024-2028 launched. source ↗

Issue: Crime and anti-social behaviour

Committed by Portsmouth City Council Proposed

No date set

Youth Justice Strategic Plan

Adopt the Youth Justice Strategic Plan and its priorities for reducing offending and reoffending by children, with final approval by Full Council.

ApprovedFundedUnder wayCompleted

Status evidence, 27 October 2026: Decision details: Portsmouth Youth Justice Strategic Plan 2026-2028 ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made 27 October 2026 · Decision details: Portsmouth Youth Justice Strategic Plan 2026-2028 ↗

Issue: Crime and anti-social behaviour

Committed by Safer Portsmouth Partnership Not verified

Past its due date (March 2026)

Community Safety Plan 2025-2028

Run a Young Futures panel pilot for children aged 10 to 17 at risk of involvement in crime, linking them to positive activities and role models.

ApprovedFundedUnder wayCompleted

No dated evidence of progress has been found; stages are shown hatched.

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made October 2025 · due March 2026 · Our priorities and plan: Community Safety Plan 2025-2028 ↗

Issue: Crime and anti-social behaviour

Committed by Police and Crime Commissioner Not verified

Due 2028

Police and Crime Plan 2024-28

Fund the recruitment of additional police officers, increase the number of Local Bobbies and open more police stations and front counters.

ApprovedFundedUnder wayCompleted

No dated evidence of progress has been found; stages are shown hatched.

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made 1 November 2024 · due 2028 · Police and Crime Plan 2024-28: More Police, Safer Streets ↗

Issue: Crime and anti-social behaviour

Homes and homelessness · 12 commitments · 8 with dated evidence · 1 past due date

Committed by Portsmouth City Council In progress

No date set

City Centre North

Work with ECF under the signed Development and Masterplanning Services Agreement on masterplanning, viability testing and a development business case, before any Development Agreement.

ApprovedFundedUnder wayCompleted

Status evidence, 10 August 2026: Partnership with ECF announced for City Centre North ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Portsmouth City Council up to £2,630,000 · Cabinet authority (10 February 2026) to spend up to an estimated £2.63m on the next phase; not a committed balance

Made 21 July 2026 · Record of Cabinet meeting, 21 July 2026 (in the 22 September 2026 Cabinet pack) ↗

2 dated records
  1. 10 February 2026 milestone Cabinet authorised spending up to an estimated £2.63m on the next phase (development business case and site surveys). A reported £18.22m spent to date could not be checked at its source. source ↗
  2. 10 August 2026 milestone Council named ECF as preferred partner after signing the Development and Masterplanning Services Agreement. A Development Agreement would need separate approval and depends on viability. source ↗

Issue: Homes and homelessness

Committed by Portsmouth City Council In progress

Due 31 March 2027

Homes for Temporary Accommodation Project

Buy and refurbish at least 200 homes to use as temporary accommodation, held in the Housing Revenue Account, with mid-year and end-of-year progress reports.

ApprovedFundedUnder wayCompleted

Status evidence, 10 March 2026: Homes for Temporary Accommodation Project: update (information report), 10 March 2026 ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Portsmouth City Council (Housing Revenue Account) £31,280,000 · Capital, 2025/26 and 2026/27
  • Funded by Portsmouth City Council (General Fund, medium-term revenue reserve) up to £1,870,000 · Up to this amount, to avoid a negative HRA cash flow in the first 10 years

Made 12 March 2025 · due 31 March 2027 · £31,280,000 (Approved HRA capital expenditure, phased £15.64m in 2025/26 and £15.64m in 2026/27. A separate General Fund contribution of up to £1.87m from the medium-term revenue reserve, approved by the Section 151 officer and noted by the Cabinet member, avoids a negative HRA cash flow in the first 10 years (not included)) · Cabinet Member for Housing and Tackling Homelessness, 12 March 2025, item 14: Acquisition of Temporary Accommodation (decision) ↗

4 dated records
  1. 12 March 2025 milestone Cabinet Member approved £31.28m HRA capital to deliver a minimum of 200 temporary accommodation homes. source ↗
  2. 31 December 2025 output 48 homes bought by 31 December 2025 (18 one-bedroom, 30 two-bedroom); a further 65 in progress, 24 of them at the legal stage. Occupancy of the bought homes is not reported. source ↗
  3. 31 December 2025 spend £7,631,102 of capital costs incurred by the end of the third quarter of 2025/26 (31 December 2025), against £31.28m approved; average purchase price about £139,000. Incurred costs, not the full approved budget or homes in use. source ↗
  4. 10 March 2026 milestone Mid-year update on the two-year project to purchase 200 homes presented and noted; homes bought so far not stated in the minutes. source ↗

Issue: Homes and homelessness

Committed by Portsmouth City Council In progress

No date set

Portsmouth Local Plan

Complete the Local Plan.

ApprovedFundedUnder wayCompleted

Status evidence, 21 October 2026: Portsmouth Local Plan: examination latest news ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made October 2024 · Corporate Plan 2024-2026 (Council Plan 2024) ↗

2 dated records
  1. 18 March 2026 milestone Council submitted the Portsmouth Local Plan to the Secretary of State for independent examination. source ↗
  2. 23 March 2026 milestone Planning Inspectorate confirmed three inspectors appointed to examine the Local Plan. source ↗

Issue: Homes and homelessness

Committed by Portsmouth City Council In progress

No date set

Nutrient Neutral Mitigation Strategy

Require new homes to be nutrient neutral, so that wastewater from development does not add nitrates to the Solent, using mitigation credits under a section 111 agreement.

ApprovedFundedUnder wayCompleted

Status evidence, 10 November 2026: Nitrate mitigation strategy ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made June 2022 · Nitrate mitigation strategy ↗

Issue: Homes and homelessness, Sewage spills and flood defences

Committed by UK Government Funded

Due 31 March 2029

Rough Sleeping Programme 2026-29

Run the Rough Sleeping Programme from 2026/27 to 2028/29 with government funding for homes and support for people sleeping rough.

ApprovedFundedUnder wayCompleted

Status evidence, 4 November 2026: Rough Sleeping Programme 2026-29 (information report), Cabinet Member for Housing and Tackling Homelessness, 4 November 2026 ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Ministry of Housing, Communities and Local Government £3,168,330 · 2026/27 to 2028/29, capital and revenue; later years provisional

Made 19 August 2026 · due 31 March 2029 · £3,168,330 (Government allocation over three years: £1,294,623 capital and £1,873,707 revenue, including £732,472 revenue in 2026/27; later years provisional. Separate from the homelessness, rough sleeping and domestic abuse grant) · Rough Sleeping Programme: funding allocations workbook ↗

1 dated record
  1. 4 November 2026 milestone Programme update presented to the housing Cabinet member, for information. On a typical autumn or winter night in 2024/25 and 2025/26 an average of 21 people were sleeping rough. source ↗

Issue: Homes and homelessness

Committed by Portsmouth City Council Approved

No date set

Magdala Road sheltered housing

Buy a vacant 14-bedroom property on Magdala Road for sheltered housing, giving at least 15 homes including a converted staff unit, let from the housing register.

ApprovedFundedUnder wayCompleted

Status evidence, 10 March 2026: Printed minutes, Cabinet Member for Housing and Tackling Homelessness, 10 March 2026 ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Portsmouth City Council (Housing Revenue Account, borrowing) £2,105,000 · Capital, 2026/27

Made 10 March 2026 · £2,105,000 (Added to the 2026/27 Housing Revenue Account capital programme, funded from borrowing) · Printed minutes, Cabinet Member for Housing and Tackling Homelessness, 10 March 2026 ↗

Issue: Homes and homelessness

Committed by UK Government Approved

Due 2035

Pride in Place programme

Fund neighbourhood regeneration in Landport and Paulsgrove through ten-year plans set by resident-led neighbourhood boards. The programme allows up to £20 million per place over ten years.

ApprovedFundedUnder wayCompleted

Status evidence, 10 November 2026: Pride in Place programme: Landport and Paulsgrove neighbourhood boards ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Ministry of Housing, Communities and Local Government up to £20,000,000 · Up to this per neighbourhood over ten years (programme limit, not approved spend)

Made September 2025 · due 2035 · Pride in Place programme prospectus ↗

1 dated record
  1. 14 August 2026 spend Landport Neighbourhood Board agreed £3,900 to Fratton Together for workshops in the Landport and Fratton West area; the council, as accountable body, signs off spending. source ↗

Issue: Homes and homelessness, Poverty, jobs and pay

Committed by Portsmouth City Council Approved

No date set

Housing Delivery Test Action Plan 2024/25

Carry out the Housing Delivery Test action plan to raise housing delivery, led by progressing the emerging Local Plan to adoption, and review the actions every year after each test result.

ApprovedFundedUnder wayCompleted

Status evidence, June 2025: Housing Delivery Test Action Plan 2024/25 ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made June 2025 · Housing Delivery Test Action Plan 2024/25 ↗

1 dated record
  1. June 2025 milestone Housing Delivery Test Action Plan 2024/25 published. source ↗

Issue: Homes and homelessness

Committed by Portsmouth City Council Proposed

No date set

City Centre North

Bring forward a mixed-use City Centre North scheme on the assembled former Tricorn and Sainsbury’s sites (potential for up to 2,300 homes). The scheme itself needs a separate Development Agreement, which depends on viability and has not been approved.

ApprovedFundedUnder wayCompleted

Status evidence, 17 October 2026: City Centre North masterplan, October 2026 (PCC41) ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made October 2024 · Corporate Plan 2024-2026 (Council Plan 2024) ↗

Issue: Homes and homelessness

Committed by Portsmouth City Council Proposed

No date set

Tipner West

Take forward Tipner West for about 1,000 homes and marine employment space, subject to Local Plan examination, habitats, bridge and funding decisions.

ApprovedFundedUnder wayCompleted

Status evidence, 17 October 2026: Portsmouth Local Plan: hearing arrangements and recordings ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made October 2024 · Corporate Plan 2024-2026 (Council Plan 2024) ↗

Issue: Homes and homelessness

Committed by Portsmouth City Council Not verified

Due 2026

Corporate Plan 2024-2026

Bring forward schemes to increase housing availability, prioritising social and affordable homes and homes for people with additional needs, and reduce the use of temporary accommodation.

ApprovedFundedUnder wayCompleted

No dated evidence of progress has been found; stages are shown hatched.

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made October 2024 · due 2026 · Corporate Plan 2024-2026 (Council Plan 2024) ↗

Issue: Homes and homelessness

Committed by Portsmouth City Council Not verified

Past its due date (December 2024)

Homelessness prevention hub (Homelessness Strategy action)

Form a multi-disciplinary prevention hub to provide advice and early intervention.

ApprovedFundedUnder wayCompleted

No dated evidence of progress has been found; stages are shown hatched.

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made February 2024 · due December 2024 · Homelessness Strategy 2024-2029 ↗

Issue: Homes and homelessness

Poverty, jobs and pay · 5 commitments · 5 with dated evidence · 0 past due date

Committed by Portsmouth City Council (port) Completed

No date set

Extend the cruise and ferry terminal with Levelling Up Fund money.

ApprovedFundedUnder wayCompleted

Status evidence, 17 October 2026: Portsmouth International Port: recent projects ↗

Who pays, key dates and what is missing
Funded by
  • Funded by UK Government (Levelling Up Fund round 1) £11,250,000 · Grant

Made October 2024 · £11,250,000 (Levelling Up Fund Round 1, as stated on the port’s recent-projects page) · Corporate Plan 2024-2026 (Council Plan 2024) ↗

1 dated record
  1. 17 October 2026 output The port’s recent-projects page describes the terminal extension as complete (retained project record; date is when it was checked). source ↗

Issue: Poverty, jobs and pay

Committed by Portsmouth City Council In progress

No date set

Connect to Work

Run Connect to Work across the Solent area (Portsmouth, Southampton and the Isle of Wight): up to 12 months of support to find and keep work for disabled people, people with health conditions and people with complex barriers to work.

ApprovedFundedUnder wayCompleted

Status evidence, 10 November 2026: Connect to Work ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Department for Work and Pensions £12,600,000 · Agreed for the whole Solent area (Portsmouth, Southampton, Isle of Wight)

Made 4 September 2025 · £12,600,000 (Agreed grant for the whole Solent area, rounded to the nearest £0.1m (DWP guidance, May 2026); an MP’s announcement of 4 September 2025 said up to £11.5m. No Portsmouth-only figure is published) · Connect to Work: Grant Guidance for England, Annex E ↗

Issue: Poverty, jobs and pay

Committed by Portsmouth City Council In progress

Due December 2029

Health Determinants Research Collaboration (HDRC Portsmouth)

Build the council’s capacity to use research on the wider causes of ill health, including community researchers and evidence to inform council decisions.

ApprovedFundedUnder wayCompleted

Status evidence, June 2026: HDRC Portsmouth: impact ↗

Who pays, key dates and what is missing
Funded by
  • Funded by National Institute for Health and Care Research £5,000,000 · About £5m over five years from January 2025, after a development year in 2024 (University of Portsmouth announcement)

Made January 2025 · due December 2029 · Collaborative Learning Island Portsmouth (CLIP): business plan, NIHR159364 ↗

Not yet published:

  • The council’s impact page has no dated milestones or counts of participants, findings published or decisions informed.
  • The Cabinet update of 4 March 2025 (noted, for information) could not be opened.
1 dated record
  1. 16 January 2025 milestone NIHR funding of about £5m over five years confirmed, starting January 2025, after a 2024 development year. source ↗

Issue: Health and access to care, Poverty, jobs and pay

Committed by Portsmouth City Council Approved

Due 2030

Skills and Labour Market Strategy 2026-2030

Deliver the Skills and Labour Market Strategy 2026-2030 through annual action plans with key performance indicators.

ApprovedFundedUnder wayCompleted

Status evidence, March 2026: Skills and Labour Market Strategy 2026-2030 ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made March 2026 · due 2030 · Skills and Labour Market Strategy 2026-2030 ↗

1 dated record
  1. March 2026 milestone Skills and Labour Market Strategy 2026-2030 published. source ↗

Issue: Poverty, jobs and pay

Committed by UK Government Approved

No date set

Devolution: combined authority investment fund

Fund the Hampshire and the Solent Combined County Authority’s investment fund at £44.6 million a year for 30 years once a mayor is in post, with a third of the annual amount in each of 2026/27 and 2027/28.

ApprovedFundedUnder wayCompleted

Status evidence, 3 June 2026: The Hampshire and the Solent Combined County Authority Regulations 2026 (SI 2026/595) ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Ministry of Housing, Communities and Local Government £44,600,000 · A year for the whole combined authority, once a mayor is in post; no Portsmouth share

Made 4 December 2025 · £44,600,000 (A year, once a mayor is in post (mayoral election planned for 4 May 2028); about £1.34 billion over 30 years is our arithmetic; no Portsmouth share is set) · Written statement HCWS1128: Devolution Priority Programme ↗

1 dated record
  1. 28 September 2026 milestone The combined authority’s board began its Local Growth Plan, naming housing, skills, connectivity, water and energy as constraints on growth. No Portsmouth share of the investment fund was set. source ↗

Issue: Poverty, jobs and pay, Council services and finances

Air pollution and traffic · 8 commitments · 7 with dated evidence · 0 past due date

Committed by Portsmouth City Council (port) Completed

No date set

Sea Change

Install shore power so ferries and cruise ships can switch off their engines at berth, serving up to three ships at once.

ApprovedFundedUnder wayCompleted

Status evidence, 17 October 2026: Sea Change shore power ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Department for Transport £19,800,000 · Grant towards shore power
  • Funded by Portsmouth City Council £4,600,000 · Council contribution
  • Funded by Portsmouth City Council £3,000,000 · Separate payment to secure grid power; not part of the £24.4m construction subtotal

Made October 2024 · £24,400,000 (£19.8m Department for Transport plus £4.6m council, as stated in the port’s go-live news; the council’s separate grid payment is excluded) · Corporate Plan 2024-2026 (Council Plan 2024) ↗

1 dated record
  1. 24 July 2026 output Ferries and cruise ships began plugging into the port’s shore power system; three ships at once was expected later in 2026. source ↗

Issue: Air pollution and traffic

Committed by Portsmouth City Council In progress

No date set

Bus Service Improvement Plan

Deliver the Bus Service Improvement Plan through the Enhanced Partnership: bus priority and bus-lane surfacing, extra services, enforcement of bus lanes, bus signal priority and upgraded “Super Stop” shelters.

ApprovedFundedUnder wayCompleted

Status evidence, 17 September 2026: LTP4 Annual Monitoring Report 2025/26 (Cabinet Member for Transport, 17 September 2026) ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Department for Transport £48,300,000 · £13m revenue and £35.3m capital, confirmed April 2022

Made April 2022 · £48,300,000 (Department for Transport funding confirmed April 2022 (£13m revenue, £35.3m capital), as stated on the council’s BSIP page) · Bus Service Improvement Plan ↗

2 dated records
  1. March 2026 output The council’s monitoring report describes red surfacing as largely delivered and 20 of 27 Super Stops installed by March 2026, fewer than the tracker’s planned 29. source ↗
  2. 10 November 2026 output The council’s delivery tracker marks bus-lane red surfacing, extra services and bus-lane enforcement (enforcement officers and tow-away) as complete, and plans 29 Super Stop shelters. Bus signal priority was delayed and planned for September 2026. source ↗

Issue: Air pollution and traffic

Committed by Portsmouth City Council In progress

No date set

Transforming Cities Fund: Portsmouth and South East Hampshire

Deliver the Portsmouth and South East Hampshire transport package, including bus priority, junction and walking improvements, with £55.6 million from the Department for Transport.

ApprovedFundedUnder wayCompleted

Status evidence, September 2026: Transforming Cities Fund Portsmouth ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Department for Transport £55,600,000 · Towards a £101.7m package across Portsmouth and South East Hampshire
  • Funded by Councils, bus operators and borough councils Match funding · Match funding for the rest of the package

Made 28 September 2020 · £55,600,000 (Department for Transport award towards a £101.7 million package, with match funding from the councils, bus operators and borough councils) · Transforming Cities Fund ↗

1 dated record
  1. 2024 spend Hampshire County Council reports the local schemes it delivered by 2024 cost £22.3 million; seven schemes are listed as completed. source ↗

Issue: Air pollution and traffic

Committed by Portsmouth City Council Approved

Due 31 March 2030

Highways PFI expiry and future services

Plan how highway maintenance will be provided when the 25-year highways PFI contract ends on 31 March 2030, through a dedicated programme team, with a full options paper (costs and risks) due at Cabinet in spring 2027.

ApprovedFundedUnder wayCompleted

Status evidence, 27 October 2026: Decision details: PFI Expiry and Future Services Programme Update ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Portsmouth City Council £3,800,000 · Phased programme budget 2024/25 to 2029/30; only 2025/26 and 2026/27 confirmed

Made 27 October 2026 · due 31 March 2030 · Cabinet, 27 October 2026: PFI Expiry and Future Services Programme Update (report) ↗

Issue: Air pollution and traffic, Council services and finances

Committed by Portsmouth City Council Approved

Due 2030

Portsmouth Transport Strategy (Local Transport Plan 4)

Deliver a ranked, provisional programme of transport schemes for 2026/27 to 2029/30 under the Transport Implementation Plan, with an outline to 2038.

ApprovedFundedUnder wayCompleted

Status evidence, July 2026: Local Transport Plan 4 page: implementation plan adopted July 2026 ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made July 2026 · due 2030 · Local Transport Plan 4: Transport Implementation Plan (adopted July 2026) ↗

1 dated record
  1. 1 July 2026 milestone Cabinet Member for Transport approved the updated Transport Implementation Plan and the Portsmouth part of a combined regional delivery plan, with a four-year government settlement of £46,524,266 (£37,618,190 capital, £8,906,076 revenue). Some area schemes remain at feasibility stage. source ↗

Issue: Air pollution and traffic

Committed by Portsmouth City Council Approved

Originally proposed by Conservative group amendment Proposal and vote →

No date set

Capital programme 2026/27: schemes added by amendment

Deliver seven small schemes added to the 2026/27 capital programme, including Anchorage Lodge refurbishment, security shutters at Drayton Park and a one-way feasibility study for Kensington Road and Chelmsford Road.

ApprovedFundedUnder wayCompleted

Status evidence, 24 February 2026: Full Council, 24 February 2026, minute 10: Budget and Council Tax 2026/27 (recorded votes) ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Portsmouth City Council (capital programme) moved within budget: £56,500 · Capital, 2026/27, moved from other schemes

Made 24 February 2026 · £56,500 (Reallocated within the capital programme) · Full Council, 24 February 2026: minutes with Appendices 1 to 3 (budget amendments), confirmed on 17 March 2026 ↗

Issue: Air pollution and traffic, Council services and finances

Committed by Portsmouth City Council Not verified

Due 2026

Corporate Plan 2024-2026

Continue to lobby and work with partners to improve air and water quality and city biodiversity.

ApprovedFundedUnder wayCompleted

No dated evidence of progress has been found; stages are shown hatched.

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made October 2024 · due 2026 · Corporate Plan 2024-2026 (Council Plan 2024) ↗

3 dated records
  1. 21 July 2026 outcome Carbon Action Plans reported to Cabinet for information: council emissions of 7,885 tonnes CO2e in 2024/25, Scope 1 and 2 about 60% below 2012/13; city emissions down 52% since 2005. source ↗
  2. 1 October 2026 outcome Air quality annual status report (information only): in 2025 one diffusion tube exceeded the annual nitrogen dioxide limit (Alfred Road, 41.86 µg/m³, kerbside, not a place of relevant public exposure, so no new management area); 225 of 228 tubes show a downward trend over 2021-2025. source ↗
  3. 10 November 2026 output The council’s water quality page describes two solar-powered LED signs on Eastney seafront, red if sewage was released in the last 48 hours, Environment Agency warning signs at Southsea East, and Yellow Fish drain markers, working with Southern Water and the Environment Agency. source ↗

Issue: Sewage spills and flood defences, Air pollution and traffic

Shared housing (HMOs) · 2 commitments · 2 with dated evidence · 0 past due date

Committed by Portsmouth City Council In progress

No date set

Additional HMO licensing

Require an additional HMO licence, citywide, for smaller shared houses (three or four people forming two or more households), alongside mandatory licensing for five or more, with enforcement for unlicensed properties.

ApprovedFundedUnder wayCompleted

Status evidence, 22 June 2026: Change to HMO licensing system ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made 1 September 2023 · Houses in Multiple Occupation (HMO) list ↗

2 dated records
  1. 10 March 2026 milestone Mandatory and additional HMO licence fees raised by 3% from 1 April 2026, to recover the full cost of licensing. source ↗
  2. 22 June 2026 milestone HMO licensing moved to the Metastreet online system. source ↗

Issue: Shared housing (HMOs)

Committed by Portsmouth City Council Approved

Originally proposed by Motion by Cllr Carl Inman and Cllr Raymond Dent Proposal and vote →

Due April 2027

Licensed HMO information

Review how licensed-HMO information is reconciled between housing and planning and published, and report the outcome to an appropriate council body within six months.

ApprovedFundedUnder wayCompleted

Status evidence, 2 November 2026: Draft minutes, Full Council 13 October 2026 ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made 13 October 2026 · due April 2027 · Full Council agenda, 13 October 2026, item 11a ↗

Issue: Shared housing (HMOs)

Schools, SEND and attendance · 4 commitments · 2 with dated evidence · 1 past due date

Committed by Portsmouth City Council Funded

Past its due date (September 2026)

Open the St George’s Inclusion Centre with 18 places from September 2026, funded from the Dedicated Schools Grant.

ApprovedFundedUnder wayCompleted

Status evidence, 7 October 2026: Dedicated Schools Grant 2026-27 Quarter 1 Budget Monitoring and Revised Budget (report to Schools Forum) ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Department for Education (Dedicated Schools Grant) Amount not stated · Revenue, from the Dedicated Schools Grant

Made 7 October 2026 · due September 2026 · Dedicated Schools Grant 2026-27 Quarter 1 Budget Monitoring and Revised Budget (report to Schools Forum) ↗

Issue: Schools, SEND and attendance

Committed by Portsmouth SEND and alternative provision partnership Approved

No date set

Local SEND Reform Plan

Deliver the Local SEND Reform Plan, centred on the Inclusion Hub and Experts at Hand early-support offer, which tracks demand for education, health and care needs assessments alongside attendance and exclusions.

ApprovedFundedUnder wayCompleted

Status evidence, 29 October 2026: Written statement HCWS431: Local SEND Reform Plan outcomes ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Local area partnership (funding sources not named in the plan) £1,405,900 · Projected spend in the first-year plan, over three quarters of 2026/27, including £69,000 for educational psychologist time in Experts at Hand

Made 18 June 2026 · The Local SEND Reform Plan – Final 2026 ↗

Issue: Schools, SEND and attendance

Committed by Portsmouth City Council Not verified

Due 2026

Corporate Plan 2024-2026

Improve support for children with special educational needs and their families, including the timeliness of education, health and care plans.

ApprovedFundedUnder wayCompleted

No dated evidence of progress has been found; stages are shown hatched.

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made October 2024 · due 2026 · Corporate Plan 2024-2026 (Council Plan 2024) ↗

2 dated records
  1. 4 December 2023 milestone In an upheld complaint, the council told the Local Government and Social Care Ombudsman it had added two SEN caseworkers and two SEN advisers, filled its SEN team vacancies, used agency staff and contracted 240 needs assessments over six months. The Ombudsman did not judge how well the plan worked. source ↗
  2. 11 June 2025 milestone Council advertised a permanent SEN caseworker post. The advert does not say whether it was a new or replacement post. source ↗

Issue: Schools, SEND and attendance

Committed by Portsmouth City Council Not verified

No date set

SENDAP Strategy 2024-2029

Improve outcomes for children and young people aged 0 to 25 with special educational needs and disabilities through the SENDAP Strategy 2024-2029, and publish a refreshed local area SEND strategy.

ApprovedFundedUnder wayCompleted

No dated evidence of progress has been found; stages are shown hatched.

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made 2024 · Portsmouth SEND and alternative provision strategy (web page) ↗

2 dated records
  1. 22 July 2026 milestone Department for Education: Portsmouth’s 2026/27 high-needs block is £32,737,303 after deductions for directly funded places (provisional until March 2027). source ↗
  2. 28 October 2026 milestone Council advertised a permanent educational psychologist post (closing 26 November 2026), including statutory assessment work. It also offers University of Southampton doctoral placements and says it wants to recruit two assistant psychologists. source ↗

Issue: Schools, SEND and attendance

Health and access to care · 10 commitments · 8 with dated evidence · 0 past due date

Committed by Portsmouth City Council Completed

No date set

Hilsea Lines Linear Park

Restore and reopen Hilsea Lido.

ApprovedFundedUnder wayCompleted

Status evidence, 17 October 2026: Hilsea Lines, reopened lido and coastal works ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made October 2024 · Corporate Plan 2024-2026 (Council Plan 2024) ↗

1 dated record
  1. 17 October 2026 output The council page says the restored lido is operated by the team behind Sea Lanes Brighton (undated page; date is when it was checked). source ↗

Issue: Health and access to care

Committed by HIVE Portsmouth In progress

Originally proposed by Healthwatch Portsmouth

No date set

HIVE Portsmouth Community Helpdesks

Run community helpdesks in Portsea (John Pounds Centre) and Paulsgrove (Paulsgrove Housing Office), giving residents in-person help to find health, care and community support.

ApprovedFundedUnder wayCompleted

Status evidence, 10 December 2025: Come and visit new HIVE Portsmouth Community Helpdesks ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Portsmouth Health and Care partnership (P3) Board Amount not stated · Funding for the two helpdesks; amount not stated

Made December 2025 · Healthwatch Portsmouth annual report 2025/26 ↗

Not yet published:

  • Current opening times should be checked with HIVE Portsmouth: the December 2025 times were described as start-up arrangements.
  • No count of people helped at the helpdesks is published. Healthwatch’s 1,474 figure covers everyone who shared experiences with it in 2025/26, not helpdesk visits.

Issue: Health and access to care

Committed by Portsmouth City Council In progress

No date set

Portsmouth Carers Strategy

Support unpaid carers through the Carers Strategy and its action plan across five priority areas, including a personalised respite and short-breaks offer.

ApprovedFundedUnder wayCompleted

Status evidence, 8 December 2025: Cabinet Member for Community Wellbeing, Health and Care, 8 December 2025: Carers’ Strategy and Action Plan update ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made January 2025 · Cabinet Member for Community Wellbeing, Health and Care, 8 December 2025: Carers’ Strategy and Action Plan update ↗

Issue: Health and access to care

Committed by Portsmouth City Council In progress

Due 2028

Autism Strategic Action Plan 2025-2028

Deliver the Autism Strategic Action Plan 2025-2028 for autistic residents and their families.

ApprovedFundedUnder wayCompleted

Status evidence, 8 December 2025: Cabinet Member for Community Wellbeing, Health and Care, 8 December 2025: Autism Strategic Action Plan update ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made 2025 · due 2028 · Cabinet Member for Community Wellbeing, Health and Care, 8 December 2025: Autism Strategic Action Plan update ↗

Issue: Health and access to care

Committed by Portsmouth City Council In progress

No date set

Bransbury Park Leisure Centre

Build a leisure and neighbourhood health hub at Bransbury Park with a 25-metre pool, learner pool, gym, studios and a GP surgery (replacing an existing practice).

ApprovedFundedUnder wayCompleted

Status evidence, 5 October 2026: Portsmouth’s new leisure and neighbourhood health hub celebrates milestones ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made October 2024 · Corporate Plan 2024-2026 (Council Plan 2024) ↗

1 dated record
  1. 5 October 2026 milestone Main structural works to both swimming pools completed. source ↗

Issue: Health and access to care

Committed by Portsmouth City Council In progress

No date set

Hilsea Lines Linear Park

Deliver the wider Hilsea Lines Linear Park around the reopened lido; separate from the lido reopening and from the coastal defence works at Hilsea Lines.

ApprovedFundedUnder wayCompleted

Status evidence, 17 October 2026: Hilsea Lines, reopened lido and coastal works ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made October 2024 · Corporate Plan 2024-2026 (Council Plan 2024) ↗

Issue: Health and access to care

Committed by Portsmouth City Council In progress

Due 2030

Smokefree Portsmouth

Bring adult smoking down to 5% or less by 2030, with specialist stop-smoking support through the Portsmouth Wellbeing Service and commissioned services, including vapes through Swap to Stop, and more quits in groups with higher smoking rates.

ApprovedFundedUnder wayCompleted

Status evidence, 17 June 2026: Stop smoking ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made October 2024 · due 2030 · Smokefree Portsmouth: a tobacco control plan 2024-2030 ↗

Outcome to watch: Adult smoking prevalence, 2025 (single year): 12.7%, England 9.5%. Target: at most 5% by 2030, 7.7 percentage points above the target. The three-year average for 2023–25 was 10.9%.

The plan states its baseline on the single-year APS series (14.7% in 2022), so the gap to the target uses the single-year series. The three-year average is steadier for comparing places. Revision: the plan quoted 13.6% (2021) and 14.7% (2022); the current OHID release gives 12.6% and 13.4% for those years. Trend and intervals →

Not yet published:

  • Stop-smoking referrals, quit attempts and four-week quits for Portsmouth by year are not published with this plan.
  • The Smokefree Generation grant amount for Portsmouth (2024/25 to 2028/29) is not stated in the plan.
  • Population smoking can change for many reasons; this record does not show the service’s effect.

Issue: Health and access to care

Committed by UK Government Approved

Due 2027

Fund 25 new dental training places at the University of Portsmouth, training dentists from 2027 onwards.

ApprovedFundedUnder wayCompleted

Status evidence, 3 June 2026: Brand new dental school places in ‘dental deserts’ ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Department of Health and Social Care (through the Office for Students) Amount not stated · Training places; amount not stated in the record

Made 3 June 2026 · due 2027 · Brand new dental school places in ‘dental deserts’ ↗

1 dated record
  1. 3 June 2026 milestone University of Portsmouth selected to host 25 new dental training places, with training from 2027. source ↗

Issue: Health and access to care

Committed by Portsmouth City Council Not verified

Due 2026

Corporate Plan 2024-2026

Continue to advocate for improved primary care in Portsmouth, including GPs, dentists and community pharmacies, and where possible partner to bring provision forward.

ApprovedFundedUnder wayCompleted

No dated evidence of progress has been found; stages are shown hatched.

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made October 2024 · due 2026 · Corporate Plan 2024-2026 (Council Plan 2024) ↗

Issue: Health and access to care

Committed by Portsmouth City Council Not verified

Due 2027

Adult Social Care Strategy 2024-2027

Shape adult social care in Portsmouth through the Adult Social Care Strategy 2024-2027.

ApprovedFundedUnder wayCompleted

No dated evidence of progress has been found; stages are shown hatched.

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made 2024 · due 2027 · Adult social care strategy 2024 - 2027 ↗

Issue: Health and access to care

Fly-tipping and street cleanliness · 3 commitments · 3 with dated evidence · 0 past due date

Committed by Portsmouth City Council Approved

Due 2035

Joint Municipal Waste Management Strategy 2026-2035

Adopt the joint waste strategy for Hampshire, Portsmouth and Southampton, with twin-stream recycling expected in future; no timetable for the action plan was set when Portsmouth approved it.

ApprovedFundedUnder wayCompleted

Status evidence, 24 September 2026: Cabinet Member for Environmental Services, 24 September 2026: decision ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made 24 September 2026 · due 2035 · Cabinet Member for Environmental Services, 24 September 2026: minutes and decision ↗

1 dated record
  1. 2 November 2026 milestone Hampshire County Council’s Executive Lead Member approved the strategy, subject to call-in; it takes effect on 11 November 2026 if not called in. source ↗

Issue: Fly-tipping and street cleanliness

Committed by Portsmouth City Council Approved

Due 2040

Hampshire Minerals and Waste Plan 2026

Plan for minerals and waste sites to 2040 under the jointly adopted Hampshire Minerals and Waste Plan. This is planning policy for sites, not household recycling collections.

ApprovedFundedUnder wayCompleted

Status evidence, 30 July 2026: Hampshire Minerals and Waste Plan 2026: adoption statement ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made 14 July 2026 · due 2040 · Hampshire Minerals and Waste Plan 2026: adoption statement ↗

Issue: Fly-tipping and street cleanliness

Committed by Portsmouth City Council Approved

No date set

Safe, Clean and Tidy

Apply a Safe, Clean and Tidy enforcement policy with visible patrols, a fly-tipping fixed-penalty scale from £400 to £1,000, hotspot mapping and review every three years.

ApprovedFundedUnder wayCompleted

Status evidence, 13 July 2026: Safe, Clean and Tidy Environmental Enforcement Policy, version 1 ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made 13 July 2026 · Safe, Clean and Tidy Environmental Enforcement Policy, version 1 ↗

1 dated record
  1. 13 July 2026 milestone Safe, Clean and Tidy enforcement policy, including the fly-tipping penalty scale, took effect. source ↗

Issue: Fly-tipping and street cleanliness

Sewage spills and flood defences · 10 commitments · 3 with dated evidence · 0 past due date

Committed by Portsmouth City Council scrutiny panel In progress

No date set

Scrutiny review: sewage discharges into the sea

Review sewage discharges into the sea around Portsmouth, taking evidence from Southern Water, the Environment Agency, the University of Portsmouth, campaign groups and Cabinet members, and report recommendations.

ApprovedFundedUnder wayCompleted

Status evidence, 3 November 2026: Traffic, Environment and Community Safety Scrutiny Panel, 3 November 2026: agenda ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made 16 July 2026 · Traffic, Environment and Community Safety Scrutiny Panel, 16 July 2026: minutes ↗

3 dated records
  1. 7 September 2026 milestone Southern Water, the Environment Agency and the University of Portsmouth gave evidence. Southern Water said 43 projects across Portsmouth aim to remove about 50 hectares of hard surface draining to sewers, ten completed, and that the Western Interceptor extension is at design stage, due to start in January 2028. source ↗
  2. 5 October 2026 milestone The Final Straw Foundation gave evidence, asking for more frequent testing at more locations, faster results and measurable targets. Action recorded: a meeting between the foundation and Southern Water, with no date set. source ↗
  3. 3 November 2026 milestone Cabinet members for climate change and for community safety gave evidence; a local resident’s written views were published. Minutes not yet published. source ↗

Issue: Sewage spills and flood defences

Committed by Portsmouth City Council In progress

Due 2028

Southsea Coastal Scheme

Build new flood defences along 4.5 km of Southsea seafront, from Old Portsmouth to Eastney, in six frontages.

ApprovedFundedUnder wayCompleted

Status evidence, 19 October 2026: Southsea Coastal Scheme booklet, October 2026 ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made October 2024 · due 2028 · £180,000,000 (The booklet gives the scheme cost as more than £180m; not a final outturn) · Southsea Coastal Scheme booklet, October 2026 ↗

4 dated records
  1. 17 March 2023 output Frontage 1 (Long Curtain Moat) officially opened. source ↗
  2. May 2024 output Frontage 4 (Southsea Castle) opened. source ↗
  3. 19 December 2024 output Frontage 5 West (Pyramids to Speakers’ Corner) opened. source ↗
  4. 2 April 2026 output Frontage 3 (Southsea Common) opened. source ↗

Issue: Sewage spills and flood defences

Committed by Portsmouth City Council In progress

Due 2027

North Portsea Coastal Scheme

Complete phase 5, the final phase of the North Portsea Coastal Scheme, at Ports Creek and Hilsea Lines.

ApprovedFundedUnder wayCompleted

Status evidence, 23 October 2026: Our final chapter begins as most of last phase opens ↗

Who pays, key dates and what is missing
Funded by
  • Funded by Environment Agency Amount not stated · Flood defence grant

Made October 2024 · due 2027 · Corporate Plan 2024-2026 (Council Plan 2024) ↗

1 dated record
  1. 23 October 2026 output Large parts of Ports Creek and Hilsea Lines opened; work continues around Peronne Road Bridge, with full completion expected in autumn 2027. source ↗

Issue: Sewage spills and flood defences

Committed by Hampshire County Council Not verified

No date set

Local Nature Recovery Strategy for Hampshire

Set priorities for nature recovery across Hampshire, including Portsmouth and Southampton, out to mean low water.

ApprovedFundedUnder wayCompleted

No dated evidence of progress has been found; stages are shown hatched.

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made November 2025 · Local Nature Recovery Strategy for Hampshire 2025, Part 1 ↗

Issue: Sewage spills and flood defences

Committed by Portsmouth City Council Not verified

No date set

Surface Water Management Plan

Reduce surface water flood risk in the fourteen hotspot areas identified in the Surface Water Management Plan (September 2025 update).

ApprovedFundedUnder wayCompleted

No dated evidence of progress has been found; stages are shown hatched.

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made September 2025 · Flood protection policies: Surface water flooding ↗

Issue: Sewage spills and flood defences

Committed by Southern Water Not verified

Due 30 June 2027

PR24 Water Industry National Environment Programme

Reduce spills from the Pier Road, Southsea storm overflow with sustainable drainage and storage (WINEP action 08SO103210a).

ApprovedFundedUnder wayCompleted

No dated evidence of progress has been found; stages are shown hatched.

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made 5 March 2025 · due 30 June 2027 · PR24 Water Industry National Environment Programme (WINEP) national dataset ↗

Issue: Sewage spills and flood defences

Committed by Southern Water Not verified

Due 30 June 2027

PR24 Water Industry National Environment Programme

Reduce spills from the Gladys Avenue, Portsmouth storm overflow with storage, sustainable drainage preferred (WINEP action 08SO103263a).

ApprovedFundedUnder wayCompleted

No dated evidence of progress has been found; stages are shown hatched.

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made 5 March 2025 · due 30 June 2027 · PR24 Water Industry National Environment Programme (WINEP) national dataset ↗

Issue: Sewage spills and flood defences

Committed by Southern Water Not verified

Due 31 March 2035

PR24 Water Industry National Environment Programme

Reduce spills from the Henderson Road, Eastney storm overflow with sustainable drainage and storage (WINEP action 08SO103190a).

ApprovedFundedUnder wayCompleted

No dated evidence of progress has been found; stages are shown hatched.

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made 5 March 2025 · due 31 March 2035 · PR24 Water Industry National Environment Programme (WINEP) national dataset ↗

Issue: Sewage spills and flood defences

Committed by Southern Water Not verified

Due 30 April 2027

PR24 Water Industry National Environment Programme

Investigate the causes of poor water quality at the Southsea East bathing water (WINEP action 08SO101010a).

ApprovedFundedUnder wayCompleted

No dated evidence of progress has been found; stages are shown hatched.

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made 5 March 2025 · due 30 April 2027 · PR24 Water Industry National Environment Programme (WINEP) national dataset ↗

Issue: Sewage spills and flood defences

Committed by Southern Water Not verified

Due 31 March 2030

PR24 Water Industry National Environment Programme

Cut spills from the Budds Farm, Havant storm overflow (permit A00751) into Langstone Harbour to fewer than 10 a year, with sustainable drainage and storage, to protect shellfish waters (WINEP action 08SO103182a).

ApprovedFundedUnder wayCompleted

No dated evidence of progress has been found; stages are shown hatched.

Who pays, key dates and what is missing
Funded by
  • Funded by Southern Water (customer bills, under Ofwat’s 2024-2030 price limits) Amount not stated · No Budds Farm cost is published; Southern Water’s 2023 business case puts its whole 2024-2030 storm overflow programme at £682m

Made 17 January 2025 · due 31 March 2030 · PR24 Water Industry National Environment Programme (WINEP) national dataset ↗

Issue: Sewage spills and flood defences

Council services and finances · 2 commitments · 1 with dated evidence · 0 past due date

Committed by Portsmouth City Council Approved

Due 31 March 2027

Budget and Council Tax 2026/27

Set a balanced 2026/27 budget with £3m of savings and a 4.99% Council Tax rise, and keep general reserves at no less than £12m at 31 March 2027.

ApprovedFundedUnder wayCompleted

Status evidence, 24 February 2026: Full Council, 24 February 2026: minutes, budget item ↗

Who pays, key dates and what is missing

Funded by: not stated in the record.

Made 24 February 2026 · due 31 March 2027 · Budget and Council Tax 2026/27, Medium-Term Budget Forecast 2027/28 to 2029/30 and Capital Strategy (report to Full Council) ↗

1 dated record
  1. 24 February 2026 milestone Full Council approved the 2026/27 budget and Council Tax, incorporating agreed amendments. source ↗

Issue: Council services and finances