Hilsea Lines moat restoration and sea defences

The fifth North Portsea coastal phase includes 1.3 km of defences at Hilsea Lines. It is separate from the lido renovation.

ProposedApprovedUnder wayCompleted
Last evidenced stage
Under way as of 17 October 2026. The council’s Hilsea Lines page says sea-defence work continues until the end of 2026.
Who owns it
Coastal Partners with the Environment Agency and Portsmouth City Council
Next decision or milestone
Published completion evidence for the final phase; end-2026 remains the published schedule.
Funding
  • Amount not stated · Environment Agency (Flood defence grant)

Earlier retained figure, not reconciled with the lines above: Not published as a single figure. Evidence: Published. Funder: North Portsea Coastal Scheme Phase 5 — Environment Agency and Coastal Partners. It is kept out of any total until its scope and date are matched.

Delivery vs outcome
Outcome evidence: The council states the wider scheme will protect over 4,000 homes and nearly 500 businesses; this is the intended protection scope, not a measured flood-loss total. An open building or working installation is delivery evidence; use, emissions or effects are outcome evidence and are reported separately.
Where
Portsmouth North

The defence route crosses north-island locations. The Hilsea place-name is not proof that its full route lies in Hilsea ward.

Dated records

  1. 2026-10-23 output Large parts of Ports Creek and Hilsea Lines opened; work continues around Peronne Road Bridge, with full completion expected in autumn 2027. source ↗