Action plan · all proposals
Proposed by Facts Count
Turn housing allocations into a deliverable programme
Publish a site-by-site delivery tracker for Portsmouth’s main housing sites, showing each site’s stage, blockers, responsible body and affordable homes, and test a permanently affordable community land trust option on public land.
In five minutes
- The evidence
Housing Delivery Test result: 11% (308 homes delivered against 2,702 required) (HDT 2025 measurement: 2022/23 to 2024/25), Portsmouth local planning authority (E06000044).
Issue: Homes and homelessness. Related findings: “Too few homes are reaching completion”, “Housing costs leave less for daily life”, “Buying a home takes many more years of pay than in 2002”, “More homes will need school, health and road capacity that is not yet secured”, “Link city promises to visible results”.
- Proposed by
Proposed by Facts Count A proposal, not a council decision or commitment.
- Proposed lead
- Portsmouth City Council (planning policy, housing supply and the council’s site promoter team), as a proposal
- Cost and funding
- Not costed · no funding identified. EstimateAllocatedSpentUnknown
- First move
- Anyone could compile and publish the site list from the council’s own September 2026 matter statements and trajectory, flagging which sites have only a resolution to grant. The council could then adopt or correct it.
- Success measure
- Completions rise towards the stepped requirement the inspectors finally accept, and the affordable share of completions becomes steadier. Each major site shows real progress from allocation to permission, start, completion and occupation. No numeric target is proposed here beyond the council’s own published trajectory, which is a forecast, not a commitment.
Suggested stages
A proposed sequence, not deadlines or funded commitments. Starting an action is not the same as its benefits arriving.
Start soon
- List every allocated and identified site with its current stage, using the council’s updated housing trajectory and matter statementsLead: Portsmouth City Council planning policy (proposed)Output: A first public site list separating allocations, resolutions to grant, permissions, starts and completionsDepends on: Updated trajectory in the Schedule of Supplementary Modifications
- Reconcile the council’s annual net completions with the government Housing Delivery Test figures and publish the reasons for the differencesLead: Portsmouth City Council planning policy (proposed)Output: A short reconciliation noteDepends on: Monitoring data from Hampshire County Council and MHCLG
- Prepare the Housing Delivery Test action plan required after the 2025 measurementLead: Portsmouth City Council planning policyOutput: Updated action plan naming site barriers and actions
Build next
- Add affordable homes by tenure (social rent, affordable rent, shared ownership) and by route (new build or acquisition) to the trackerLead: Portsmouth City Council housing supply (proposed)Output: Tenure table for each site and year
- Scope a community land trust option: identify a willing community group, candidate council land, legal form, governance, finance and resale or rent controlsLead: Portsmouth City Council housing supply with a community-led housing adviser (proposed)Output: Feasibility note with costs, risks and a go or no-go recommendationDepends on: Interest from residents or an existing organisation
- Set out the funding route and timing for City Centre North and Tipner West enabling works, including any Homes England business caseLead: Portsmouth City Council site promoter teamOutput: Published funding status for each strategic siteDepends on: Homes England and combined authority funding decisions
Longer term
- Report completions, occupied homes and affordable tenure against the adopted trajectory every year, and explain slippage by siteLead: Portsmouth City Council planning policy (proposed)Output: Annual delivery report linked to the authority monitoring report
- If the feasibility work supports it, pilot a small permanently affordable scheme on council landLead: Community land trust or registered provider partner with the council (proposed)Output: Pilot scheme with a lasting affordability mechanism
Why, and the trade-off
Too few homes are being finished. Government counted about 308 net homes in the three years to March 2025, against 2,702 needed. The big sites that should supply most homes face hard barriers: flood defences, polluted land, protected bird habitat, road changes and weak viability. City Centre North has had a resolution to grant since 2023 but is being redesigned. Tipner West has an estimated £107m funding gap. Affordable completions vary sharply from year to year.
Trade-off: Lower-income households, families in temporary accommodation and younger workers would gain most from more affordable homes. Shared ownership helps a different, higher-income group than social rent. Existing residents near big sites may face years of construction. Land given to a community trust benefits its members, so allocation rules need to be open and fair.
Related projects: City Centre North — former Tricorn and Sainsbury’s sites, Tipner West
Where the homes are: New homes and build sites · Local projects
Baseline Housing Delivery Test result: 11% (308 homes delivered against 2,702 required) (HDT 2025 measurement: 2022/23 to 2024/25); Net homes added, council monitoring: 316 net homes (2025/26 (year to 31 March 2026)); Affordable homes completed (all routes): 59 (41 bought existing homes, 18 newly built) (2024/25); Affordable homes completed through planning schemes (gross): 15 of 259 gross completions (6%) (2024/25); Planned five-year housing land supply on adoption: 5.37 years (council estimate) (2027/28 to 2031/32, assuming adoption in spring 2027); House price to residents’ pay: 7.22 times (2025)
Full appraisal
Problem, options against the current approach, costs, risks, who gains and who pays, and how progress would be judged.
Full delivery plan: problem, options, costs, risks and how to judge progress
The problem and who is affected
Too few homes are being finished. Government counted about 308 net homes in the three years to March 2025, against 2,702 needed. The big sites that should supply most homes face hard barriers: flood defences, polluted land, protected bird habitat, road changes and weak viability. City Centre North has had a resolution to grant since 2023 but is being redesigned. Tipner West has an estimated £107m funding gap. Affordable completions vary sharply from year to year.
Who is affected: Households waiting for a settled or affordable home, including 608 households in temporary accommodation in March 2026; younger workers and families priced out by rents and prices; and residents near large sites who live with long-term vacant or derelict land.
| Measure | Value | Period | Area |
|---|---|---|---|
| Housing Delivery Test result Unrounded delivered figure 308.50, including a communal accommodation adjustment. Annual delivery: 8.7, 289.5 and 10.2 homes. Below 75% triggers an action plan, a 20% land supply buffer and the unmet-need test in NPPF policy S5(1)(j). | 11% (308 homes delivered against 2,702 required) | HDT 2025 measurement: 2022/23 to 2024/25 | Portsmouth local planning authority (E06000044) |
| Net homes added, council monitoring Council monitoring figure. It is not on the same basis as the government test and the two series have not been reconciled. | 316 net homes | 2025/26 (year to 31 March 2026) | Portsmouth City Council area |
| Affordable homes completed (all routes) 273 in 2023/24 and 177 in 2022/23. Acquisitions convert existing homes; they do not add to total housing stock. | 59 (41 bought existing homes, 18 newly built) | 2024/25 | Portsmouth (E06000044) |
| Affordable homes completed through planning schemes (gross) 149 of 311 (48%) in 2023/24. Different scope from the government affordable supply table. | 15 of 259 gross completions (6%) | 2024/25 | Portsmouth City Council area |
| Planned five-year housing land supply on adoption A forecast that depends on the inspectors’ conclusions and on 825 completions expected in 2026/27. | 5.37 years (council estimate) | 2027/28 to 2031/32, assuming adoption in spring 2027 | Portsmouth City Council area |
| House price to residents’ pay Median house price divided by median full-time resident annual pay. It measures individual pay, not household mortgage eligibility. | 7.22 times | 2025 | Portsmouth (E06000044) |
What this would change
Aim: Turn the homes promised in the Local Plan into finished, occupied homes, with a clear share that local people on lower incomes can afford over the long term.
What success would mean: Completions rise towards the stepped requirement the inspectors finally accept, and the affordable share of completions becomes steadier. Each major site shows real progress from allocation to permission, start, completion and occupation. No numeric target is proposed here beyond the council’s own published trajectory, which is a forecast, not a commitment.
Publish and update a public site-by-site tracker covering every allocated and identified site. For each site it would show the planning stage, the main blocker (flood defence, contamination, habitat mitigation, road works, viability, vacant possession or funding), who must act, the next decision, and planned and actual affordable homes by tenure. Separate allocations, resolutions to grant, permissions, starts, completions and occupied homes. Use the council’s land at City Centre North, Tipner West and smaller council sites to test a permanently affordable community land trust option alongside existing council and housing association delivery.
Proposed lead: Portsmouth City Council (planning policy, housing supply and the council’s site promoter team), as a proposal. Partners: Homes England, Registered providers of social housing, Muse/ECF (appointed City Centre North master developer), Environment Agency and Coastal Partners (flood defences), Natural England (habitat mitigation), Hampshire and the Solent Combined County Authority (from its funding powers), A community land trust or community-led housing group, if one forms.
Powers: The council is the local planning authority and must keep an up-to-date plan, monitor delivery and, under NPPF Annex D, prepare a Housing Delivery Test action plan when delivery falls below 95% (nppf-2026). It owns City Centre North and Tipner West and can choose disposal terms, partners and tenure as landowner (pcc-m701, pcc-tipner-delivery-approach). It cannot force private developers to build out a permission, set government grant, or fund flood defences alone; the Infrastructure Delivery Plan says Tipner West defences must be funded by the developer (pcc-idp-2026). A community land trust would need its own legal form and governance; the council can transfer or lease land but must meet its own disposal and subsidy rules, which have not been checked here.
Options
The council’s trajectory, the inspectors’ findings and Homes England funding decisions could all change the right choice. A tracker is low cost but does not itself build homes. A community land trust depends on a group forming, on land being made available below market value and on finance; national experience may not transfer to a dense island city where nearly all homes will be flats. Funding gaps at Tipner West and City Centre North could make cross-subsidy for permanent affordability harder.
Delivery plan
| Stage | Task | Proposed lead | Dependencies and decisions | Output |
|---|---|---|---|---|
| Start soon | List every allocated and identified site with its current stage, using the council’s updated housing trajectory and matter statements | Portsmouth City Council planning policy (proposed) | Depends on: Updated trajectory in the Schedule of Supplementary Modifications | A first public site list separating allocations, resolutions to grant, permissions, starts and completions |
| Start soon | Reconcile the council’s annual net completions with the government Housing Delivery Test figures and publish the reasons for the differences | Portsmouth City Council planning policy (proposed) | Depends on: Monitoring data from Hampshire County Council and MHCLG | A short reconciliation note |
| Start soon | Prepare the Housing Delivery Test action plan required after the 2025 measurement | Portsmouth City Council planning policy | Decision: Publication of the 2025 results on 17 August 2026 triggered the requirement; no new plan was found on 2 November 2026 | Updated action plan naming site barriers and actions |
| Build next | Add affordable homes by tenure (social rent, affordable rent, shared ownership) and by route (new build or acquisition) to the tracker | Portsmouth City Council housing supply (proposed) | — | Tenure table for each site and year |
| Build next | Scope a community land trust option: identify a willing community group, candidate council land, legal form, governance, finance and resale or rent controls | Portsmouth City Council housing supply with a community-led housing adviser (proposed) | Depends on: Interest from residents or an existing organisation · Decision: Cabinet decision on whether to offer land or a covenant | Feasibility note with costs, risks and a go or no-go recommendation |
| Build next | Set out the funding route and timing for City Centre North and Tipner West enabling works, including any Homes England business case | Portsmouth City Council site promoter team | Depends on: Homes England and combined authority funding decisions | Published funding status for each strategic site |
| Longer term | Report completions, occupied homes and affordable tenure against the adopted trajectory every year, and explain slippage by site | Portsmouth City Council planning policy (proposed) | Decision: Adoption of the Portsmouth Local Plan, expected by the council in spring 2027 | Annual delivery report linked to the authority monitoring report |
| Longer term | If the feasibility work supports it, pilot a small permanently affordable scheme on council land | Community land trust or registered provider partner with the council (proposed) | — | Pilot scheme with a lasting affordability mechanism |
A first practical step: Anyone could compile and publish the site list from the council’s own September 2026 matter statements and trajectory, flagging which sites have only a resolution to grant. The council could then adopt or correct it.
Costs and funding
- One-off costs
- Not costed. The tracker is mainly officer time; the community land trust feasibility study would need specialist legal and financial advice.
- Recurring costs
- Not costed. Updating the tracker twice a year would need monitoring staff time.
- Capital or revenue
- Tracker: revenue. Community land trust homes: capital (land, build or purchase) plus a small revenue cost for governance support.
- Funding status
- No funding identified for the tracker or a community land trust. Homes England’s Social and Affordable Homes Programme 2026 to 2036 lists community-led housing as a national priority, but no Portsmouth bid was found.
- Affordability
- The council faces large funding gaps on its own strategic sites (about £107m at Tipner West). Giving land at below market value for permanent affordability would reduce receipts that could otherwise close those gaps.
- Costing still needed
- Estimate staff days for the tracker; for the community land trust, estimate land value forgone, build or purchase cost per home, grant per home, rent or resale levels, and long-term management costs.
Benefits, risks and trade-offs
Possible benefits: Residents and councillors could see which sites are stuck and why, who must act, and whether affordable homes are actually being built. A permanently affordable model could stop discounts being lost when homes are resold. These benefits are not quantified.
Risks:
- A tracker could be read as a delivery commitment when stages and dates remain forecasts.
- Large sites may stay stalled because of funding gaps, whatever the reporting.
- A community land trust may not find a group, land or finance, and could be small and slow.
- Giving council land at below market value could worsen viability on strategic sites.
- Different definitions (government test, council monitoring, affordable supply table) could confuse readers if not explained.
Who could gain or lose: Lower-income households, families in temporary accommodation and younger workers would gain most from more affordable homes. Shared ownership helps a different, higher-income group than social rent. Existing residents near big sites may face years of construction. Land given to a community trust benefits its members, so allocation rules need to be open and fair.
Environment: Strategic sites sit next to Portsmouth Harbour, which is protected for birds, and parts of Tipner West are in flood zones 2 and 3. Delivery must include habitat mitigation, nutrient neutrality and new sea defences.
Capacity: The council’s 2024/25 action plan linked part of past under-delivery to planning service performance. Tracking, reconciling data and supporting a community land trust would need staff time in planning policy, housing supply and legal services, none of which is costed or allocated here.
How to judge progress
| Measure | Definition | Starting point | Source and area | How often · who reports |
|---|---|---|---|---|
| Housing Delivery Test result | Net homes delivered over three years as a share of homes required | 11% (308 of 2,702), HDT 2025 | hdt-2025-results · Portsmouth local planning authority | Annual, when MHCLG publishes · MHCLG |
| Net completions | Net additional homes completed in the monitoring year (council method) | 316 in 2025/26 | pcc-table6 · Portsmouth City Council area | Annual · Portsmouth City Council |
| Affordable completions by tenure and route | Affordable homes completed by social rent, affordable rent and shared ownership, split into new build and acquisitions | 59 in 2024/25 (41 acquisitions, 18 new build; 15 social rent, 41 affordable rent, 3 shared ownership) | mhclg-ahs-open-data · Portsmouth (E06000044) | Annual · MHCLG |
| Sites moving stage | Number of allocated sites moving from allocation to permission, start, completion and occupation each year | No published baseline Gap: No tracker exists; the council publishes stages in its trajectory and monitoring report but not as a regular stage count. | Proposed site tracker · Portsmouth City Council area | Twice a year (proposed) · Not agreed |
| Homes held as permanently affordable | Homes with a legal mechanism that keeps them affordable on resale or reletting, such as community land trust ownership | No published baseline Gap: No local count of permanently affordable or community-led homes was found. | Not available · Portsmouth City Council area | Annual (proposed) · Not agreed |
Reassess when: Reassess when the inspectors report on the Local Plan, when MHCLG publishes the next Housing Delivery Test, or when Homes England decides on Tipner West or City Centre North funding.
Where things stand
What is known:
- The 2025 Housing Delivery Test result is 11%: 308 homes against 2,702 required.
- The Local Plan was submitted on 18 March 2026 and hearings are running; Tipner West is now due to be heard on 19 November 2026.
- City Centre North has had a resolution to grant since 25 October 2023 but the council now assumes 1,600 homes, not 2,300, and first completions in 2029/30.
- Tipner West has an estimated funding gap of about £107m and no committed public funding.
- Affordable completions fell from 273 in 2023/24 to 59 in 2024/25.
What is not known:
- Why the government test and council monitoring give different annual totals for the same years.
- How many homes on each site are or will be social rent.
- Whether the inspectors will accept the stepped requirement and site trajectories.
- Whether any community group in Portsmouth wants to form a community land trust.
- When the Housing Delivery Test action plan responding to the 2025 result will be published.
Decisions needed:
- Whether the council will publish a site-by-site delivery tracker and how often.
- Whether to reconcile and publish the differences between the government test and council monitoring.
- Whether to commission a community land trust feasibility study and offer council land for it.
- How affordable housing on council-owned strategic sites will be secured through disposal terms.
Existing work:
- Portsmouth Local Plan examination: Hearings in progress; Tipner West, Lakeside North Harbour and Horsea Island moved to 19 November 2026; housing land supply and viability on 26 November 2026 (as of 2026-10-21).
- Housing Delivery Test Action Plan 2024/25: Published June 2025 in response to the 2023 test (26%); it names site constraints, market change, land assembly, nutrient neutrality and planning service performance (as of 2025-06).
- City Centre North (22/01243/CS3): Resolution to grant conditional permission on 25 October 2023; promoter now preparing a revised application; master developer Muse/ECF appointed under a development management agreement (as of 2026-09-18).
- Tipner West (Policy PLP3): Allocation under examination for about 1,000 homes and 25,000 m² employment; council owns the freehold but leaseholders remain; funding gap about £107m (as of 2026-09-18).
- Tipner East (Policy PLP4): 835-home Vivid scheme (22/01292/FUL) under construction; 221-home Bellway scheme (21/01357/FUL) had a resolution to grant with permission expected in autumn 2026 (as of 2026-09-18).
- Future Portsmouth Plan: Council started a new-system local plan on 14 July 2026; the current plan continues as a legacy plan (as of 2026-07-14).
UK Facts context: Housing supply: from permission to a finished home (National explainer of the stages from permission to completion; Portsmouth figures here are local.) · Housing remedies (National options and funding mechanisms; not a Portsmouth assessment.)
Next review: When the Local Plan inspectors issue their post-hearing letter or report, or when MHCLG publishes the next Housing Delivery Test measurement.. Evidence last checked 2026-11-02.
Sources
MHCLG: Housing Delivery Test result ↗ · Housing Delivery Test: 2025 measurement ↗ · National Planning Policy Framework (August 2026) ↗ · Portsmouth Local Plan: examination updates ↗ · ID04 Initial Hearing Programme, version 7 ↗ · Portsmouth City Council response to the Inspectors’ questions, Matter 7: sites allocated and identified in the plan (M7.01) ↗ · Portsmouth City Council response to the Inspectors’ questions, Matter 2: housing need and requirement (M2.01) ↗ · Portsmouth City Council response to the Inspectors’ questions, Matter 8: housing policies (M8.01) ↗ · Portsmouth City Council response to the Inspectors’ questions, Matter 14: housing land supply (M14.01) ↗ · Portsmouth City Council response to the Inspectors’ questions, Matter 15: viability, delivery and monitoring (M15.01) ↗ · Portsmouth City Council PCC39, updated Housing Background Paper Table 6 ↗ · Authority Monitoring Report 2024/25 (PCC01) ↗ · Affordable housing supply open data, 1991-92 to 2024-25 ↗ · Housing Delivery Test Action Plan 2024/25 ↗ · City Centre North masterplan, October 2026 ↗ · Planning Committee minutes, 25 October 2023 ↗ · Pre-Submission Portsmouth Local Plan Addendum 2025 ↗ · Submission Suggested Main Modifications V2.0 ↗ · Tipner West Regeneration Delivery Approach (SS35) ↗ · Tipner West Topic Paper (TP10) ↗ · PCC35 Infrastructure Delivery Plan (supersedes IN16) ↗ · ONS: Median house price / median resident annual earnings ↗ · Social and Affordable Homes Programme (SAHP) 2026 to 2036 ↗ · Local Plan Timetable for the Future Portsmouth Plan ↗ · MHCLG: Households in temporary accommodation ↗Where earlier ideas went
- housing-delivery-plan (earlier 12-point plan): expanded. This action; baseline 308 against 2,702 retained and verified; site tracker, tenure reporting and options added.
- clt-housing (earlier ten suggestions): restored. Candidate option ‘Community land trust or permanently affordable homes on council land’ with scoping task, costs, risks and an evaluation metric. Not carried forward: The 17,700-home Local Plan target (not found; the submitted requirement is 11,369, proposed to change to 11,090); the target of several hundred trust homes by the early 2030s (no evidence); ‘tens of millions’ cost (no checkable origin); short-term letting claim (not sourced); MOD and Crown Estate land (no specific site found); London CLT and St Clements examples (not checked).
UK-wide context
Sources
- MHCLG: Housing Delivery Test result checked 2026-10-03
- Housing Delivery Test: 2025 measurement checked 2026-11-02
- National Planning Policy Framework (August 2026) checked 2026-11-02
- Portsmouth Local Plan: examination updates checked 2026-10-17
- ID04 Initial Hearing Programme, version 7 checked 2026-11-02
- Portsmouth City Council response to the Inspectors’ questions, Matter 7: sites allocated and identified in the plan (M7.01) checked 2026-11-02
- Portsmouth City Council response to the Inspectors’ questions, Matter 2: housing need and requirement (M2.01) checked 2026-11-02
- Portsmouth City Council response to the Inspectors’ questions, Matter 8: housing policies (M8.01) checked 2026-11-02
- Portsmouth City Council response to the Inspectors’ questions, Matter 14: housing land supply (M14.01) checked 2026-11-02
- Portsmouth City Council response to the Inspectors’ questions, Matter 15: viability, delivery and monitoring (M15.01) checked 2026-11-02
- Portsmouth City Council PCC39, updated Housing Background Paper Table 6 checked 2026-10-17
- Authority Monitoring Report 2024/25 (PCC01) checked 2026-11-02
- Affordable housing supply open data, 1991-92 to 2024-25 checked 2026-11-02
- Housing Delivery Test Action Plan 2024/25 checked 2026-11-02
- City Centre North masterplan, October 2026 checked 2026-10-17
- Planning Committee minutes, 25 October 2023 checked 2026-11-02
- Pre-Submission Portsmouth Local Plan Addendum 2025 checked 2026-11-02
- Submission Suggested Main Modifications V2.0 checked 2026-11-02
- Tipner West Regeneration Delivery Approach (SS35) checked 2026-11-02
- Tipner West Topic Paper (TP10) checked 2026-11-02
- PCC35 Infrastructure Delivery Plan (supersedes IN16) checked 2026-11-02
- ONS: Median house price / median resident annual earnings checked 2026-10-03
- Social and Affordable Homes Programme (SAHP) 2026 to 2036 checked 2026-11-02
- Local Plan Timetable for the Future Portsmouth Plan checked 2026-11-02
- MHCLG: Households in temporary accommodation checked 2026-10-03