Action plan · all proposals
Proposed by Facts Count
Measure what cleaner shipping and transport actually deliver
Publish how often ships use the new shore power, how much electricity they take and what emissions are avoided, and report nearby air quality and the Pompey Link bus pilot, so results can be judged against forecasts.
In five minutes
- The evidence
Annual mean nitrogen dioxide at London Road automatic station: 27.97 µg/m³ (objective 40) (2025), London Road monitoring station.
Issue: Air pollution and traffic. Related findings: “The port and university give the city a strong base”, “Shore power can cut emissions while ships are berthed”.
- Proposed by
Proposed by Facts Count A proposal, not a council decision or commitment.
- Proposed lead
- Portsmouth City Council (proposed; as port owner, air quality authority and local transport authority)
- Cost and funding
- Not costed · no funding identified. EstimateAllocatedSpentUnknown
- First move
- Write to the port asking which shore power usage figures it already collects and could publish in aggregate. This needs no new funding or approval.
- Success measure
- Regular published figures for ship connections, electricity used and estimated emissions avoided, set against the forecast; air quality results near the port reported alongside them; and a published evaluation of Pompey Link before any decision to extend or end it. No numeric target is proposed, because no agreed baseline exists yet.
Suggested stages
A proposed sequence, not deadlines or funded commitments. Starting an action is not the same as its benefits arriving.
Start soon
- Agree with the port which shore power figures can be published and at what level of aggregation.Lead: Portsmouth City Council with Portsmouth International PortOutput: Agreed data list and first publication date
- Identify which existing diffusion-tube and automatic monitoring sites are closest to the port berths and approach roads.Lead: Portsmouth City Council regulatory servicesOutput: Published list of port-relevant monitoring sites and 2021–2025 resultsDepends on: Full 2026 ASR (available on request)
- Publish Pompey Link passengers, cost per journey and a short user survey summary.Lead: Portsmouth City Council transportOutput: Pilot evaluation note
Build next
- Publish the first quarterly shore power summary with the method for estimating avoided emissions.Lead: Portsmouth International PortOutput: Quarterly summaryDepends on: Agreed data list
- Compare air quality near the port before and after shore power, allowing for weather and traffic.Lead: University of Portsmouth with the councilOutput: Short technical note with uncertaintyDepends on: Monitoring data and baseline from the project
Longer term
- Decide on any extension to the remaining two berths or further bus pilots using the published evidence and a costed operating plan.Lead: Portsmouth City Council (as port owner and transport authority)Output: Published decision with evidence
Why, and the trade-off
The port now offers shore power, so docked ships can switch off their engines. The port forecasts a large carbon saving from 2027, but it has published no figures on how often ships connect, how much electricity they use or what emissions are avoided. Operators say the electricity is too expensive, so use may stay low. Air quality and greenhouse gases are measured in separate ways, and bus and port money come from different budgets. Without clear reporting, residents cannot tell what these schemes achieve.
Trade-off: People living near the port and busy roads would gain most if ships plug in. Pompey Link users include people in areas without another bus route; ending the pilot without evaluation could leave them worse off. Public subsidy of electricity for ships would transfer money to operators and would need justification.
Related projects: Sea Change shore power, Pompey Link on-demand bus pilot, Portsmouth International Port — cruise and ferry terminal
Baseline Annual mean nitrogen dioxide at London Road automatic station: 27.97 µg/m³ (objective 40) (2025); Air Quality Management Areas in force: 5 (AQMAs 6, 7, 9, 11, 12) (2025 monitoring year, reported October 2026); Territorial greenhouse gas emissions, all sources: 653 kt CO2e, of which transport 234 kt (36%) (2024); Shore power connections, electricity supplied and emissions avoided: Not published (Since July–August 2026); Pompey Link passengers and cost per journey: Not published (Pilot since 2025)
Full appraisal
Problem, options against the current approach, costs, risks, who gains and who pays, and how progress would be judged.
Full delivery plan: problem, options, costs, risks and how to judge progress
The problem and who is affected
The port now offers shore power, so docked ships can switch off their engines. The port forecasts a large carbon saving from 2027, but it has published no figures on how often ships connect, how much electricity they use or what emissions are avoided. Operators say the electricity is too expensive, so use may stay low. Air quality and greenhouse gases are measured in separate ways, and bus and port money come from different budgets. Without clear reporting, residents cannot tell what these schemes achieve.
Who is affected: People who live and work near the port and along busy roads such as Alfred Road, London Road and the port approaches. Bus users in the north of the city served by the Pompey Link pilot. Council taxpayers, who part-funded the port works. Ferry and cruise operators deciding whether to plug in.
| Measure | Value | Period | Area |
|---|---|---|---|
| Annual mean nitrogen dioxide at London Road automatic station | 27.97 µg/m³ (objective 40) | 2025 | London Road monitoring station |
| Air Quality Management Areas in force | 5 (AQMAs 6, 7, 9, 11, 12) | 2025 monitoring year, reported October 2026 | Portsmouth |
| Territorial greenhouse gas emissions, all sources Excludes international shipping and most port-related ship emissions; cannot measure Sea Change. | 653 kt CO2e, of which transport 234 kt (36%) | 2024 | Portsmouth local authority area |
| Shore power connections, electricity supplied and emissions avoided Only a forecast of over 20,000 t CO2e a year from 2027 is published. | Not published | Since July–August 2026 | Portsmouth International Port |
| Pompey Link passengers and cost per journey | Not published | Pilot since 2025 | Paulsgrove, Port Solent and Cosham |
What this would change
Aim: Show, in public and in plain numbers, whether shore power and local bus pilots are being used and what they change for air quality, carbon emissions and access.
What success would mean: Regular published figures for ship connections, electricity used and estimated emissions avoided, set against the forecast; air quality results near the port reported alongside them; and a published evaluation of Pompey Link before any decision to extend or end it. No numeric target is proposed, because no agreed baseline exists yet.
The council, as owner of the port and as local transport authority, would ask the port to publish a quarterly shore power summary: connected calls by vessel type, hours connected, electricity supplied, share of eligible calls that connected, and estimated emissions avoided with the method stated. The council would publish the port-area air quality monitoring sites and results from the existing network. For Pompey Link, it would publish passengers, cost per journey and who uses it before the funding decision. Bus and port reporting stay separate because their funding and purposes differ. Cycling is covered in the separate cycle-connections action.
Proposed lead: Portsmouth City Council (proposed; as port owner, air quality authority and local transport authority). Partners: Portsmouth International Port, University of Portsmouth (Sea Change monitoring partner), Brittany Ferries and other port customers, Community First (Pompey Link operator), Stagecoach South and First Solent (bus enhanced partnership).
Powers: The council has statutory local air quality management duties and must report through the Annual Status Report (asr2026-summary). As local transport authority it holds the statutory Local Transport Plan and the bus enhanced partnership (ltp4-amr-2026, bsip-page). As owner of the port it can ask the port to publish operational data; this is an organisational choice, not a statutory power, and commercial data about individual operators may need to be aggregated. The council cannot make ships connect and does not set national electricity costs, which the port and operators say are the main barrier (seachange-whitepaper).
Options
Further appraisal may change the choice because the cost of data collection, commercial confidentiality with ship operators, and whether the monitoring network can separate port effects from traffic and weather are not yet known.
Delivery plan
| Stage | Task | Proposed lead | Dependencies and decisions | Output |
|---|---|---|---|---|
| Start soon | Agree with the port which shore power figures can be published and at what level of aggregation. | Portsmouth City Council with Portsmouth International Port | Decision: Port and operators confirm what is commercially publishable | Agreed data list and first publication date |
| Start soon | Identify which existing diffusion-tube and automatic monitoring sites are closest to the port berths and approach roads. | Portsmouth City Council regulatory services | Depends on: Full 2026 ASR (available on request) | Published list of port-relevant monitoring sites and 2021–2025 results |
| Start soon | Publish Pompey Link passengers, cost per journey and a short user survey summary. | Portsmouth City Council transport | Decision: Before the decision on funding after March or May 2027 | Pilot evaluation note |
| Build next | Publish the first quarterly shore power summary with the method for estimating avoided emissions. | Portsmouth International Port | Depends on: Agreed data list | Quarterly summary |
| Build next | Compare air quality near the port before and after shore power, allowing for weather and traffic. | University of Portsmouth with the council | Depends on: Monitoring data and baseline from the project | Short technical note with uncertainty |
| Longer term | Decide on any extension to the remaining two berths or further bus pilots using the published evidence and a costed operating plan. | Portsmouth City Council (as port owner and transport authority) | Decision: Measured use and a funded operating plan | Published decision with evidence |
A first practical step: Write to the port asking which shore power usage figures it already collects and could publish in aggregate. This needs no new funding or approval.
Costs and funding
- One-off costs
- Not costed. Setting up reporting from data the port already holds is expected to be small, but this has not been estimated.
- Recurring costs
- Not costed. Staff time for quarterly publication and any extra monitoring analysis.
- Capital or revenue
- Mainly revenue (reporting and analysis). Existing Sea Change capital was £19.8m government funding plus £4.6m council match, with a separate council grid contribution given as £3.6m in the September 2026 white paper (seachange-whitepaper) and as £3m in the July 2026 press release (seachange-golive); the two sources have not been reconciled. None of this pays for reporting.
- Funding status
- No funding identified for reporting. Bus grant (£7.46m revenue over 2026/27–2028/29) is ring-fenced for bus projects and cannot pay for port works.
- Affordability
- Not assessed. Reporting costs should be estimated before any commitment.
- Costing still needed
- Estimate staff days for quarterly port reporting and an annual air quality comparison; confirm whether the Sea Change demonstrator budget already covers monitoring until the end of the demonstration period.
Benefits, risks and trade-offs
Possible benefits: Residents and councillors could see whether a large public investment is used. Evidence would show whether low uptake needs action on electricity costs. A Pompey Link evaluation would support a fair decision on its future. Benefits are not quantified.
Risks:
- Ship operators may connect rarely because electricity is expensive, so the forecast saving may not happen.
- Air quality near the port is affected by traffic, weather and other sources, so changes may not be attributable to shore power.
- Commercial confidentiality may limit what the port can publish about individual operators.
- Reporting creates staff workload without new funding.
- Local greenhouse gas statistics will not show the effect, which could be misread as failure or success.
Who could gain or lose: People living near the port and busy roads would gain most if ships plug in. Pompey Link users include people in areas without another bus route; ending the pilot without evaluation could leave them worse off. Public subsidy of electricity for ships would transfer money to operators and would need justification.
Environment: Shore power is intended to cut fuel burnt at berth, noise and local pollution. Its carbon effect depends on the electricity source; the port says supply is 100% renewable, which was not independently checked.
Capacity: The council runs the monitoring network and the port, but no dedicated reporting post was identified. The University of Portsmouth monitoring role is tied to the demonstrator period.
How to judge progress
| Measure | Definition | Starting point | Source and area | How often · who reports |
|---|---|---|---|---|
| Share of eligible ship calls that connected to shore power | Calls at the three shore power berths where the vessel connected, divided by calls by vessels able to connect | Not established Gap: No published baseline or agreed reporting arrangement | Portsmouth International Port operational records · Portsmouth International Port | Quarterly (proposed) · Portsmouth International Port (proposed) |
| Electricity supplied to ships (MWh) and estimated CO2e avoided | Metered shore power electricity; avoided emissions estimated with a stated fuel-displacement method, compared with the 20,000 t a year forecast | Not established; forecast only Gap: No published data or method | Port metering; Sea Change project method · Portsmouth International Port | Quarterly (proposed) · Portsmouth International Port (proposed) |
| Annual mean NO2 and PM2.5 at monitoring sites nearest the port | Annual means from existing diffusion tubes and automatic stations, compared with 2021–2025 | Site list not yet identified; London Road 27.97 µg/m³ is not port-specific Gap: Port-relevant sites need to be named; full ASR is not publicly posted | Annual Status Report · Port-adjacent monitoring sites | Annual · Portsmouth City Council |
| Pompey Link passengers and net cost per passenger journey | Passenger journeys and council subsidy divided by journeys | Not published Gap: No published figures | Council and Community First records · Paulsgrove, Port Solent and Cosham zones | Quarterly during pilot (proposed) · Portsmouth City Council (proposed) |
Reassess when: Reassess when the port publishes any usage figures, when the 2027 Annual Status Report (2026 data) is published, or when the Pompey Link funding decision is due.
Where things stand
What is known:
- Sea Change serves the three busiest berths and began commercial use in July–August 2026.
- Government provided £19.8m and the council £4.6m in match funding, plus a grid contribution.
- The 20,000 t CO2e a year saving is a forecast from 2027.
- Air quality objectives were met at relevant exposure in 2025, but most sites worsened compared with 2024.
- Local greenhouse gas statistics do not capture international shipping.
- Pompey Link is a pilot funded through the BSIP.
What is not known:
- How many ships have connected and how much electricity they used.
- The method behind the 20,000 t forecast.
- Which monitoring sites best represent the port area.
- Whether Pompey Link funding ends in March or May 2027, and its cost and use.
- The shore power tariff and whether it is subsidised.
- Whether three ships have yet connected at the same time.
Decisions needed:
- Whether the council, as port owner, asks for regular public shore power reporting.
- Whether to fund an independent evaluation after the demonstrator period.
- Whether to extend, change or end Pompey Link, based on published evidence.
Existing work:
- Sea Change shore power: Operating; first commercial connections July–August 2026 (as of 2026-09).
- Annual Status Report of Air Quality 2026 (2025 data): Published as a summary to the 1 October 2026 meeting; full report on request (as of 2026-10-01).
- Pompey Link on-demand bus pilot: Operating; funded to March 2027 (service page) or May 2027 (monitoring report) (as of 2026-10-05).
- Portsmouth Bus Service Improvement Plan: £48.3m programme 2022–2026; new multi-year bus grant from 2026/27 (as of 2026-07-22).
- Portsmouth Transport Strategy (LTP4) 2021–2038: Adopted October 2021; fourth monitoring report September 2026 (as of 2026-09-17).
Next review: When the port publishes shore power usage data, or when the council publishes the 2027 Annual Status Report summary, or at the Pompey Link funding decision.. Evidence last checked 2026-11-02.
Sources
Council-owned port: Sea Change shore power ↗ · Plugging in: Portsmouth’s shore power journey and the future of clean ports (white paper) ↗ · It’s electrifying – Portsmouth International Port’s shore power system goes live ↗ · Portsmouth City Council: NO₂ annual mean — London Road ↗ · 2005 to 2024 UK local and regional greenhouse gas emissions – data tables ↗ · Local and regional greenhouse gas emissions estimates for 2005–2024: technical report ↗ · Council transport service: Pompey Link ↗ · Bus Service Improvement Plan – Getting Portsmouth on the bus ↗ · LABG revenue allocations: 2026 to 2029 ↗ · Local Transport Plan 4 Annual Monitoring Report 2025/26 (Cabinet Member for Transport, 17 September 2026) ↗ · Local Transport Plan 4 – Implementation Plan 2026/2027 (Cabinet Member for Transport, 19 March 2026) ↗Where earlier ideas went
- cleaner-transport (earlier 12-point plan): expanded. cleaner-transport Not carried forward: Nothing dropped. The claim that no combined cost is published is corrected: itemised Sea Change capital funding is now published. Cycling moved to the separate cycle-connections action.
Sources
- Council-owned port: Sea Change shore power checked 2026-10-17
- Plugging in: Portsmouth’s shore power journey and the future of clean ports (white paper) checked 2026-11-02
- It’s electrifying – Portsmouth International Port’s shore power system goes live checked 2026-11-02
- Portsmouth City Council: NO₂ annual mean — London Road checked 2026-10-03
- 2005 to 2024 UK local and regional greenhouse gas emissions – data tables checked 2026-11-02
- Local and regional greenhouse gas emissions estimates for 2005–2024: technical report checked 2026-11-02
- Council transport service: Pompey Link checked 2026-10-17
- Bus Service Improvement Plan – Getting Portsmouth on the bus checked 2026-11-02
- LABG revenue allocations: 2026 to 2029 checked 2026-11-02
- Local Transport Plan 4 Annual Monitoring Report 2025/26 (Cabinet Member for Transport, 17 September 2026) checked 2026-11-02
- Local Transport Plan 4 – Implementation Plan 2026/2027 (Cabinet Member for Transport, 19 March 2026) checked 2026-11-02