City Centre North
2,300 homes. Preferred partner chosen. City centre, Commercial Road.
1 · What is planned
Homes and stage
Masterplan aspiration “up to 2,300”. The council told the Local Plan inspectors in September 2026 that about 1,600 is more realistic after viability and reduced building heights.
Where it stands: English Cities Fund selected as preferred regeneration partner in August 2026 to develop a business case; no development agreement verified. The council proposed moving first completions to 2029/30.
Planning (22/01243/CC3): Resolution to grant in 2023; the scheme is being redesigned and its capacity has changed since (council evidence, September 2026, which writes the reference as 22/01243/CS3). Reference reported from the council register, which blocks scripted access.
2 · Can I buy?
First-time buyers
Not a near-term buying lead: no sales arrangements or launch date.
Affordable and social homes
An earlier first-phase design of 550 apartments was described as 70% private sale and 30% affordable, split between affordable rent and shared ownership. Not a confirmed schedule after partner selection.
Earlier proposal.
3 · Who is involved
Developer, builder and land
- Developer
- English Cities Fund (Muse, Legal & General, Homes England’s National Housing Bank): preferred partner
- Builder
- Not appointed
- Who sells or lets
- Not established
- Land
- The council has assembled substantial ownership; some parcels need title-level checking. Reported
Public money: The partnership covers masterplanning, viability and a business case. No agreed land price, rent, profit share, subsidy or construction budget is published. Not found
4 · Roads, schools and doctors
What comes with the homes
“Proposed” means part of the scheme or application. “Not found” means no secured obligation could be verified, not that none exists.
- Schools Not found No signed schedule verified.
- SEND places Not found Not verified.
- GP and health Not found Not verified.
- Parking Not found Not verified.
- Public space proposed Public space, commercial uses and walking and cycling connections in the masterplan.
5 · Energy
Heating and solar
No phase-by-phase heating, solar or Future Homes Standard schedule found.
The Future Homes Standard regulations are due to come into force on 24 March 2027 with transitional arrangements; whether they apply to a building depends on its building-control application and commencement dates. Solar panels, heat pumps or an A-rated certificate do not by themselves show compliance, and compliance does not require a heat pump in every flat.
The council’s Local Plan view
Ownership, constraints and open questions
- Ownership
- The council promotes the site; the wider city-centre allocation is partly council-owned. Confirm the ownership of each parcel.
- Proposal
- The council retains an aspiration for 2,300 homes, but told the inspectors that viability and reduced building heights made about 1,600 more realistic in September 2026. Neither is a completion commitment.
- Status
- The council said Muse/ECF had been appointed to develop a business case before a possible development agreement. It proposed moving first completions to 2029/30, rather than 2027/28; this is a forecast, not a promise.
- Constraints
- Land assembly, finance, design, infrastructure and the mix of affordable homes require further evidence.
- Open question
- Has a development agreement been signed, and what is the current application, funding and phased timetable?
Council response to inspectors, Matter 7, paragraphs 7.26.3 and 7.29.1, September 2026 ↗
Evidence
What each statement rests on
- Checked Council aspiration of 2,300 homes; about 1,600 more realistic because viability concerns reduced building heights; first completions moved to 2029/30 (September 2026 evidence). Portsmouth City Council ↗
- Checked English Cities Fund (Homes England’s National Housing Bank, Legal & General and Muse) was named preferred partner on 10 August 2026. A Development and Masterplanning Services Agreement was signed; a full Development Agreement would follow only if viability work supports it. Construction Enquirer ↗, Portsmouth City Council ↗, Portsmouth City Centre ↗
- Response to inspectors, Matter 7 (September 2026) ↗ Portsmouth City Council, cited in the research of 10 November 2026
- Portsmouth picks ECF for 2,300-home city centre regeneration (10 August 2026) ↗ Construction Enquirer, cited in the research of 10 November 2026
- Partnership with English Cities Fund announced (2026) ↗ Portsmouth City Council, cited in the research of 10 November 2026
- City Centre North project page ↗ Portsmouth City Centre, cited in the research of 10 November 2026
Still missing
- Development agreement, funding and phased timetable.
- Final tenure mix.
- School, SEND, GP and parking provision.